Westcote, Reading

Westcote Build Process

PROJECT DETAILS

After the internal strip-out the previous week the diggers were bought in for week 1 of the external demolition.
This week’s main achievements were to set up site facilities, cabins, portable washroom and knock down of the bungalow.

 
 

WEEK ONE

 

After the internal strip-out the previous week the diggers were bought in for week 1 of the external demolition. This week’s main achievements were to set up site facilities, cabins, portable washroom and knock down of the bungalow.

 

WEEK TWO

 

Once the bungalow was fully demolished all the rubble had to be cleared out of site.

 

WEEK THREE

 

More clearance work started in preparation for the preparation for the foundation. Signage was added.

 

WEEK FOUR

 

The foundations are being dug out in preparation for the concrete to be poured in the following week.

 

WEEK FIVE/SIX

 

Pouring the concrete mix using a large pump.

 

WEEK SEVEN

 
 

WEEK EIGHT

 

We are not above the ground and DPC level!